

OHC reviewed the design phase for the total
removal of all mold, asbestos, lead and hazardous materials within the
12-story, 300,000 square foot Bennett Building located in Jacksonville
Florida. OHC is presently performing the project oversight and monitoring
during all asbestos and hazardous material remediation activities. The
schedule for the remediation activities on this project is one year.
Pre-Bid Meeting-
OHC’s project manager and designer conducted the meeting with all
respective bidders to cover the scope of work.
Bid Evaluation-
Upon receipt of the bids and qualification package OHC assisted GSA and
Skanska with the bid analysis and preparation of the bid award.
Pre-Construction meeting-
project schedule, milestone dates, site access, safety and security, chain
of command, and pre-job submittals were discussed in the meeting.
Pre-job Submittal review-
OHC reviewed and approved all submittals. Some of the required submittals
included; asbestos and lead plan, site specific safety and health plan,
fire protection plan, fall protection plan, lock out/tag out, scaffolding,
hazard communication, emergency response and contingency plan.
Project Supervision and Monitoring:
OHC was responsible for the initial, and daily inspection of the integrity
of the enclosure, using smoke tubes to test airflow within the
containment, continuous monitoring of pressure differential within the
containment, and perimeter air monitoring throughout the project.
Clearance Testing:
Upon completion of abatement in each work area
OHC conducted a visual clearance in accordance with ASTM-E 1368-00
protocol. Air sample clearances were performed following the TEM NIOSH
7402 protocol.
Project Close-out:
Post-job submittals were reviewed and approved
to complete project closeout.
OHC has been servicing the GSA Southeastern
United States Regions for the past 7 years for the Tampa and Jacksonville
districts. OHC is on contract on as needed basis to respond to any IAQ
issues for all the buildings owned or managed by GSA throughout the
Northern region of Florida. GSA has requested that OHC maintains a
response team especially trained for emergency response to biological
warfare type agents. OHC maintains all the necessary equipment and
training to respond to any such attacks. OHC has performed various types
of indoor air quality investigations for GSA including initial preliminary
screenings, limited and full IAQ surveys, HVAC remediation and
retrofitting and testing for various biological agents including
Anthrax.
Some of these investigations have been initiated on an emergency basis,
requiring swift response to building occupant complaints. OHC has been
able to respond quickly to the concerns of building occupants and has
provided crucial information to GSA management and to concerned personnel,
thereby quelling their concerns. Many of these IAQ surveys have been high
profile in nature.
back to main
page